Paving project set to begin on turnpike

A 15 mile paving project is set to begin Monday, April 28, which may cause some delays along I-70. The project will stretch between East Topeka and the Lecompton/Lawrence exits on I-70.

All three lanes in both directions will be covered during this project. Work will begin near the Lecompton/Lawrence exit on the center lane between 6 p.m. and 6 a.m. Traffic will be reduced to one lane during that time.

**********************

This 15-mile section of 6-lane roadway is the Turnpike’s heaviest traveled so motorists are urged to check for construction updates at http://www.kandrive.org <http://www.kandrive.org/&gt;, follow the Kansas Turnpike on Twitter, and watch for information on the KTA’s digital message boards.
The project will involve covering all three lanes in both directions with an ultrathin bond asphalt surface. Shoulders will also be sealed with a spray seal.
While timing of work will be updated throughout the project, the current schedule is below. Each segment of the project is expected to take 4-5 days unless noted otherwise.
· The contractor will start with patching work near the Lecompton/Lawrence exit. Much of this work will be in the center lane so it will be completed at night, between 6:00 p.m. and 6:00 a.m. and will take 2-4 days. Traffic will be reduced to one lane when work is being completed in the center lane.
· Following patching, overlaying will begin on the inside lanes during the day.
· The center lane will then be overlayed. This will take place at night due to the need to close two lanes in order to safely do the work.
· Work will then move to the outside lanes.
· When all lane work is complete, the ramps at 197 will be overlayed, followed by sealing the shoulders along the entire project.
· After a two-week window for the project to cure, roadway lines will be painted.